Ongoing Projects
Security Cameras
Update 6/23/25
New security camera system will be installed Monday, June 23, 2025. Argus Security has taken on the project. Security is important to our community, and an active security camera system is foundational to preventative security systems.
​

Perimeter Wall Behind O-Building
Update 6/23/25
The historic storm from March 2025 left parts of our perimeter wall in ruins. It has taken months to get competent contractors on site to get bids. A contract to begin work has been secured as of June 20, 2025. Insurance does not cover our perimeter wall.
​
​​​
​

Perimeter Wall by Gate
Update 6/23/25
This piece of wall was also damaged during the historic storm from March 2025. We will be breaking ground the week of June 23, 2025.

Entrance Gate
Update 6/23/25
Our brand new gate operator for the entrance was completely submerged during the March 2025 historic floods. Unfortunately, warranty does not cover flood or water damage. We currently have two bids in from different vendors, and are awaiting a third as of June 23, 2025. Insurance does not cover our gate.

Bay Front Pipe (Sinkhole)
This project has been completed as of May, 2025.
A reinforced concrete pipe (RCP) was discovered to be split northwest of the bay front Gazebo. Rain and drainage throughout the years has caused erosion in that area. Previous efforts to fill the hole lead to the investigation into the RCP. The specialized nature of this project has lead to delays in most of the process.